Sunday, 13 September 2020

7th September 2020

Category: Hull, Deck Work

Maintenance/Repair Details:
Week 1: Boat lifted at Allington Marina for her annual service, anti-fouling and anode replacement. During the first week she was washed down, polished and rubbing band sanded and re-varnished. New coat of anti-foul applied. New magnesium anodes fitted as we intend on staying at Allington in fresh water.
Week 2: Area of the saloon roof which were chipped or worn away rubbed down and repainted, chrome work cleaned and fenders cleaned (removed old fender socks). General clean of interior and carpets.
Week 3: Boat safety inspection carried out (replace glass sediment fuel bowls with metal ones). Refurbish & reproof winter canopy ready for fitting.

Parts and/or Items Used:
Anodes, Anti-fouled Paint, Gloss Paint, Wood Preserver.

No comments:

Post a Comment